ENVIRONMENT AGENCY AGREES START DATE FOR TYNE DREDGING


Environmental Panorama
International
August of 2009


The Environment Agency confirmed today that it has agreed that dredging in the bed of the River Tyne for the second Tyne Tunnel can start on 26 September.

The dredging has to be carried out with care to avoid causing problems to the environment, particularly migrating salmon on their way to breed in the upper Tyne catchment. The Tyne is one of the best salmon rivers in England and studies have shown that each rod-caught salmon can generate as much as £4,600 for the local economy.

Previously the government had made it a condition that the dredging should take place in the winter months to avoid the salmon migration season – however new methods of both dredging and disposal mean this important operation can now be brought forward.

The improved system uses a suction-cutting dredger, which will suck sediment and water up and reduce the amount of silt that would be disturbed by the more usual bucket or ‘back-hoe’ dredger.

The silt will then be transferred 1.5 km downstream via an enclosed pipe system, and used to fill the now redundant Tyne Dock. Once the dock has been filled it will be commercially developed by the Port of Tyne Authority. This disposal will avoid an estimated 4,600 lorry journeys through built-up areas, and also means there will be no dumping at sea.

John Hogger, the Environment Agency’s area environment manager, said: “This scheme for dredging the tunnel trench will have a significantly lower risk to the environment overall than the previous proposals. However we still have to ensure that impacts are minimised, especially for the salmon stocks.

“We have set the start date to avoid the summer period when existing water quality can cause problems for salmon migrating through the estuary. There should be no need for extra releases from Kielder Reservoir, as the water quality should have improved by that time. However this is always an option in extreme circumstances.

“We have also imposed minimum water quality thresholds to protect the ecology of the estuary. We’ll be monitoring the water quality continuously during the operation at several key points around the dredge site and the Tyne Dock to measure the level of waterborne sediment and dissolved oxygen in the river and help ensure water quality stays above these preset thresholds.
“If the water quality drops below our thresholds then work has to stop until the dredging activity can be modified.

“We’ll also be monitoring the numbers of fish passing the fish counters at our Riding Mill site to control any impact from dredging. Should the numbers fall below a preset minimum level over a five day period then dredging will be suspended.”

Once the tunnel sections have been placed in the dredged trench ‘clean’ material will be used to fill the trench. This will be inert sand taken from the navigation channel in the mouth of the Tyne, an area regularly dredged by the Port Of Tyne Authority.
Although the six week dredging period could start in late September, it is expected that the bulk of the work will happen in late October and November, with dredging actually taking place for around half of the six weeks.

The Environment Agency believes the risks to fish stocks will be very low, and has stringent controls in place should this change.

+ More

Environment Agency uses barges to build flood banks

Engineers are taking to the water as they start work to improve flood defences near Goole. - The Environment Agency is using barges on the River Ouse during the first stages of work on the £11.9 million flood defence scheme at Swinefleet.

A crane and piling machine upon the 30 metre long barge - called the Maverick - will be used to carry out the works that will better protect 9,400 homes and 1,200 commercial properties from flooding when complete.

Once anchored, the Maverick and its 80 tonne crane move up and down with the water level, which enables engineers to work through the changing tides.

The 24 metre long crane that sits on the Maverick is used to work sheet piles up to 15.5 metres long into the bank that will form the new flood embankment. The improvements will raise and widen the embankment as well as improving its stability.

Will Benedikz, project manager for the Environment Agency, said: ”At this stage of the scheme we are working in people’s back gardens.

“Using the river instead of the land allows us to cause the least disruption to the community. It also prevents us damaging the existing banks with construction traffic.”

The Environment Agency will also be using the Humber Estuary to bring materials into the site. Four barges will bring steel piles onto the site via the estuary, saving 85 wagon journeys through Swinefleet.

The scheme is one of the first to be built following the publication last year of the Humber Strategy, a 100 year plan for flood risk management around the estuary, through a partnership the Environment Agency has set up with specialist engineering firm Birse Civils, with design consultants Halcrow and Black & Veatch.

The partnership will be investing £36 million in flood alleviation schemes for Swinefleet and Brough on the north bank of the Humber, and Stallingborough and Halton Marshes in North Lincolnshire.

 
 

Source: Environment Agency – United Kingdom
Press consultantship
All rights reserved

 
 
 
 

 

Universo Ambiental  
 
 
 
 
     
VEJA
NOTÍCIAS AMBIENTAIS
DIVERSAS
Acesse notícias variadas e matérias exclusivas sobre diversos assuntos socioambientais.

 
 
 
 
Conheça
Conteúdo
Participe
     
Veja as perguntas frequentes sobre a Agência Ecologia e como você pode navegar pelo nosso conteúdo.
Veja o que você encontrará no acervo da Agência Ecologia. Acesse matérias, artigos e muito mais.
Veja como você pode participar da manutenção da Agência Ecologia e da produção de conteúdo socioambiental gratuito.
             
 
 

 

 

 

 
 
 
 
 
     
ACESSE O UNIVERSO AMBIENTAL
DE NOTÍCIAS
Veja o acervo de notícias e matérias especiais sobre diversos temas ambientais.

 
 
 
 
Compromissos
Fale Conosco
Pesquise
     
Conheça nosso compromisso com o jornalismo socioambiental independente. Veja as regras de utilização das informações.
Entre em contato com a Agência Ecologia. Tire suas dúvidas e saiba como você pode apoiar nosso trabalho.
A Agência Ecologia disponibiliza um banco de informações ambientais com mais de 45 mil páginas de conteúdo online gratuito.
             
 

 

 

 

 

 

 
 
 
 
 
 
Agência Ecologia
     
DESTAQUES EXPLORE +
SIGA-NOS
 

 

 
Agência Ecologia
Biodiversidade Notícias Socioambientais
Florestas Universo Ambiental
Avifauna Sobre Nós
Oceano Busca na Plataforma
Heimdall Contato
Odin Thor
  Loki
   
 
Direitos reservados. Agência Ecologia 2024-2025. Agência Ambiental Pick-upau 1999-2025.